Energy & Risk Reduction Programme Case Study 4
Swindon data centre. Improvements were recommended in the following areas:- Install blanking plates
- Curtains (for containment) and return grilles to network rows
- Reduce pressure set points
- Seal gaps in aisles where cabinets are missing
- Relocate poorly placed floor grilles
- Cold aisle containment
- Review scoop direction
- Change cabinet doors to increase open area/airflow
- Angled grilles
- Improve processes for Colo installations